Aim
- Create a design project and build an exhibition stand 5 days before the start of the exhibition (not before the start of installation). At the same time, outside the working schedule, without technical specifications, materials and free installers! A client of JSC "SIA" addressed us with such a request on the eve of the exhibition "Transport Week of Russia", which was held in November in Gostiny Dvor in Moscow.
28 m²
Construction area
4
Teams of installers
3
Night shifts
5 days
From order to delivery
Exponic
2025
Result
- Event chronology: on November 13 the customer approved the design project of the stand, on November 14, technical drawings were developed, and only at that moment it became clear what materials are needed for the stand, which still need to be purchased, what size all the elements that still need to be filed, etc. And on November 15 installation begins, construction is only for 3 days and on the evening of the 17th must be delivered to the customer.
- During the installation, there was an urgent task to make a glowing pylon, which clearly demonstrated the composition and levels of which the runway was created.
- The exposition turned out to be aerial with an imitation of a runway in two planes and airport windows in the terminal. To give a glossy and smooth surface, the technology of stretch ceilings was used. The floors were made of laminated MDF.
- The stand received an award from the organizers for the "Most avant-garde stand".